Welcome to the new Schneider Electric Community

It's your place to connect with experts and peers, get continuous support, and share knowledge.

  • Explore the new navigation for even easier access to your community.
  • Bookmark and use our new, easy-to-remember address (community.se.com).
  • Get ready for more content and an improved experience.

Contact SchneiderCommunity.Support@se.com if you have any questions.

Close
Invite a Co-worker
Send a co-worker an invite to the Exchange portal.Just enter their email address and we’ll connect them to register. After joining, they will belong to the same company.
Send Invite Cancel
84463members
353666posts

Can below feature be programmed in ION 7650 - "MD Integration Period is 15 Minutes with sub integration period of 5 minutes with sliding window method."

Metering & Power Quality

Collaborate with multiple experts and discuss various topics about Power Meters and Power Quality. From design & implementation to troubleshooting and more, get support from experts and share your experiences by subscribing to the Schneider Electric Exchange forum today.

Solved
sesa354877
Schneider Alumni (Retired)
Schneider Alumni (Retired)
0 Likes
1
140

Can below feature be programmed in ION 7650 - "MD Integration Period is 15 Minutes with sub integration period of 5 minutes with sliding window method."

MD Integration Period is 15 Minutes with sub integration period of 5 minutes with sliding window method. Is it possible to configure ION7650 for this feature?


Accepted Solutions
Robert_Lee
Captain Captain
Captain
0 Likes
0
114

Re: Can below feature be programmed in ION 7650 - "MD Integration Period is 15 Minutes with sub integration period of 5 minutes with sliding window method."

I assume MD is some type of Power Demand which to answer your question, yes you can modify the default demand period use to compute demand from the default of a single period of 15 minutes to 3 x 5 minute sub-intervals.  ION Setup will do this fairly easily while using ION Designer is a bit more tedious.

7650_demand.png

See Answer In Context

1 Reply 1
Robert_Lee
Captain Captain
Captain
0 Likes
0
115

Re: Can below feature be programmed in ION 7650 - "MD Integration Period is 15 Minutes with sub integration period of 5 minutes with sliding window method."

I assume MD is some type of Power Demand which to answer your question, yes you can modify the default demand period use to compute demand from the default of a single period of 15 minutes to 3 x 5 minute sub-intervals.  ION Setup will do this fairly easily while using ION Designer is a bit more tedious.

7650_demand.png