Hi All,
Has anyone installed / or has DCO 7.5 been tested on a ProLiant G9 server with RAID6 (P-series controller)?
(CID:99157515)
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2020-07-02 02:25 PM . Last Modified: 2024-04-09 04:12 AM
Hi David,
DCO 7.5 has not been tested on a ProLiant G9 server, but the normal server requirements applies. Please see the server requirements here
If you have problems installing with the normal installer then please install with Alternative drivers option. This option is used for installing DCO on newer hardware. More information about installing with alternative drivers can be seen here
Thanks
Jesper
(CID:99157527)
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2020-07-02 02:25 PM . Last Modified: 2024-04-09 04:12 AM
Hi David,
DCO 7.5 has not been tested on a ProLiant G9 server, but the normal server requirements applies. Please see the server requirements here
If you have problems installing with the normal installer then please install with Alternative drivers option. This option is used for installing DCO on newer hardware. More information about installing with alternative drivers can be seen here
Thanks
Jesper
(CID:99157527)
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2020-07-02 02:25 PM . Last Modified: 2024-04-09 04:12 AM
Thanks Jesper
(CID:99157528)
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2020-07-02 02:26 PM . Last Modified: 2024-04-09 04:12 AM
Hi David,
We have been testing the installation of DCO 7.5 on ProLiant G9, the only install option for this server at the moment is installing on Red Hat enterprise linux 6.x and the running the DCO RHEL installation as described Installing StruxureWare Data Center Operation on Red Hat Enterprise Linux
Thanks
Frank
(CID:99157928)
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2020-07-02 02:26 PM . Last Modified: 2024-04-09 04:12 AM
Hi Frank, Kindly advise on the detailed linux code to execute this installation, I am also having this issue and am not fully comfortable in doing this. Regards, Felix
(CID:105457508)
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2020-07-02 02:26 PM . Last Modified: 2024-04-09 04:12 AM
Hi Felix, We are willing to support you in this on a remote basis, what we would need to start out with is a server running redhat enterprise linux with a subscription to 'RHEL EUS Optional' would that help you going forward? Installing the traditional ISO on a G9 is not possible, and will not be possible. Best Regards Frank
(CID:105457512)
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2020-07-02 02:26 PM . Last Modified: 2024-04-09 04:12 AM
Hi Frank, Thank you for your prompt response. Please avail your contacts to me, I already have the redhat enterprise linux OS installed on the Server with no subscription. Regards, Felix
(CID:105457526)
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2020-07-02 02:26 PM . Last Modified: 2024-04-09 04:12 AM
Hi Frank, Kindly is it possible for me to be assisted remotely before breaking for chrismass holiday, this project is complete only awaiting the DCO server. Thank you. Regards, Felix
(CID:105457663)
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2020-07-02 02:26 PM . Last Modified: 2024-04-09 04:12 AM
Hi Felix, I have send you an email Regards Frank
(CID:105458378)
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2020-07-02 02:26 PM . Last Modified: 2023-10-31 10:49 PM
This question is closed for comments. You're welcome to start a new topic if you have further comments on this issue.
Link copied. Please paste this link to share this article on your social media post.
Create your free account or log in to subscribe to the board - and gain access to more than 10,000+ support articles along with insights from experts and peers.