Issue
A Schedule or PE program can not change the value of a point because it is set by another process at a higher Command Priority.
Product Line
Andover Continuum
Environment
- CyberStation
- bCX4040
- B3s
Cause
Command value must be Relinquished at the priority that no longer needs to control the point's value so that a command with a lower priority can take control of it.
Resolution
Edit the point from the BACnet view.
Go to the Command Priority tab, this tab shows the 16 priorities and their current statuses
Select the priority to relinquish and then click on the Relinquish button.
The command with the next highest priority should then immediately take over.