vcenter 7, PCNS 4.4.2 shutting down vcenter then cancelling hoist shutdown
APC UPS Data Center & Enterprise Solutions Forum
Schneider, APC support forum to share knowledge about installation and configuration for Data Center and Business Power UPSs, Accessories, Software, Services.
Send a co-worker an invite to the portal.Just enter their email address and we'll connect them to register. After joining, they will belong to the same company.
You have entered an invalid email address. Please re-enter the email address.
This co-worker has already been invited to the Exchange portal. Please invite another co-worker.
Please enter email address
Send InviteCancel
Invitation Sent
Your invitation was sent.Thanks for sharing Exchange with your co-worker.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2022-05-1202:45 AM
vcenter 7, PCNS 4.4.2 shutting down vcenter then cancelling hoist shutdown
Hi,
I am having an issue where the PCNS correctly shuts down all of the VM's in the correct order, then gets to the final stage where it then shuts down the vcenter, causing the maintenance mode to get cancelled and the host shutdown to stop.
my vcenter is in the high priority section of vm prioritisation.
sequence of events form log file:-
shutting down hosts on .....
after quite a while i get shutting down vm vcenter_7.0
maintance mode task cancelled as vcsa vm is shutting down
cannont connect to vcenter so may not eb able to issue commands to vm's or hosts.
shutdown host unsuccsesful for host....
any ideas would be helpful as i am a little stuck?
Without seeing the EventLog.txt file, error.log. and debug.log, I cannot be sure, but my guess is credentials. Once vCenter has been powered off, PowerChute must connect directly to the ESXi host. The shutdown will fail if the credentials used to connect to vCenter do not exist on the ESXi host.
To create the proper credentials, see the PowerChute VMware User's Guide starting on page 59