Hi,
I have a couple of questions:
Thanks! Ray
Posted: 2021-07-08 11:28 PM
This reply was originally posted by Juan on APC forums on 7/15/2019
1- If you set a 0 second duration for a priority group, the migration action will be skipped for all VMs in that priority group.
2- Waits 120 seconds even if the task finished before or later. Then starts the next group depending if its migrating , shutdown or starting.
3- I used the Youtube channel for some configuration and the user guide for PCNS 4.3
Posted: 2021-07-08 11:28 PM
This reply was originally posted by Juan on APC forums on 7/15/2019
1- If you set a 0 second duration for a priority group, the migration action will be skipped for all VMs in that priority group.
2- Waits 120 seconds even if the task finished before or later. Then starts the next group depending if its migrating , shutdown or starting.
3- I used the Youtube channel for some configuration and the user guide for PCNS 4.3