Welcome to the new Schneider Electric Community

It's your place to connect with experts and peers, get continuous support, and share knowledge.

  • Explore the new navigation for even easier access to your community.
  • Bookmark and use our new, easy-to-remember address (community.se.com).
  • Get ready for more content and an improved experience.

Contact SchneiderCommunity.Support@se.com if you have any questions.

Close
Invite a Co-worker
Send a co-worker an invite to the Exchange portal.Just enter their email address and we’ll connect them to register. After joining, they will belong to the same company.
Send Invite Cancel
84245members
353345posts

ABOUT THE PM710

Metering & Power Quality

Collaborate with multiple experts and discuss various topics about Power Meters and Power Quality. From design & implementation to troubleshooting and more, get support from experts and share your experiences by subscribing to the Schneider Electric Exchange forum today.

Solved
AYSEGUL
Ensign Ensign
Ensign
0 Likes
1
498

ABOUT THE PM710

Dears All hello,

There is a peak demand current on display of PM710. Is this peak current value monthly? or Is the maximum current value up to this day? Customer wants to see the peak current from installed on field to today.

 

Thanks for your support.

 

B&R

Ayşegül

 

Tags (1)

Accepted Solutions
Charles_Murison
Picard Picard
Picard
0 Likes
0
492

Re: ABOUT THE PM710

Hello @AYSEGUL ,

 

Please note the PM700 is an old meter and no longer officially supported. The meter does have a current peak demand measurement that is the maximum current demand since the last demand reset. If customer wants this as a monthly value, the demand would need to be read at the start of each month and then reset. 

 

You can find some information on the meter from the following links


https://www.se.com/ww/en/download/document/63230-501-207/  (Reference guide)
https://www.se.com/ww/en/download/document/63230501201A3/ (Instruction Bulletin)

https://www.se.com/ww/en/download/document/3000DB0807/ ( Quick start)

 

Regards,

Charles

L4 Prime for Advanced metering and Utilities

See Answer In Context

Tags (1)
1 Reply 1
Charles_Murison
Picard Picard
Picard
0 Likes
0
493

Re: ABOUT THE PM710

Hello @AYSEGUL ,

 

Please note the PM700 is an old meter and no longer officially supported. The meter does have a current peak demand measurement that is the maximum current demand since the last demand reset. If customer wants this as a monthly value, the demand would need to be read at the start of each month and then reset. 

 

You can find some information on the meter from the following links


https://www.se.com/ww/en/download/document/63230-501-207/  (Reference guide)
https://www.se.com/ww/en/download/document/63230501201A3/ (Instruction Bulletin)

https://www.se.com/ww/en/download/document/3000DB0807/ ( Quick start)

 