Hello,
I have a customer that is using splitters to feed their racks, so there is only one 3-phase circuit feeding both in-rack PDUs. Is there a way to properly reflect this in DCO for capacity planning? Possibly a wiring device I can't find in the genome?
Thanks,
--Jeff
(CID:133368620)
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2020-07-04 09:23 PM . Last Modified: 2024-04-04 03:41 AM
Hi Jeff
No direct support AFAIK but happy to hear differently. You can always get a model done in some way but you may have to make a compromise, usually either in asset or capacity management. Im away from my systems right now but my first thought is to use a DCO PDU to represent the splitter, as you will be able to manage capacity of splitter (PDU) as well as both rpdus. but.... AFAIK DCO PDUs must be floor mounted. Are your spillers rack mounted? or above rack? elsewhere. this might take some playing to get the best mix of DCO cap man features.
i hope that helps
cheers
Ed
(CID:133369147)
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2020-07-04 09:23 PM . Last Modified: 2023-10-22 04:36 AM
This question is closed for comments. You're welcome to start a new topic if you have further comments on this issue.
Link copied. Please paste this link to share this article on your social media post.
Create your free account or log in to subscribe to the board - and gain access to more than 10,000+ support articles along with insights from experts and peers.
With achievable small steps, users progress and continually feel satisfaction in task accomplishment.
Usetiful Onboarding Checklist remembers the progress of every user, allowing them to take bite-sized journeys and continue where they left.
of