Schneider Electric Building Automation Knowledge Base is a self-service resource to answer all your questions about EcoStruxure Building suite, Andover Continuum, Satchwell, TAC…
Send a co-worker an invite to the portal.Just enter their email address and we'll connect them to register. After joining, they will belong to the same company.
You have entered an invalid email address. Please re-enter the email address.
This co-worker has already been invited to the Exchange portal. Please invite another co-worker.
Please enter email address
Send InviteCancel
Invitation Sent
Your invitation was sent.Thanks for sharing Exchange with your co-worker.
The instance values the Function Block program had when the backup was taken is lost when the backup is restored in an AS-P running in PCT.
Product Line
EcoStruxure Building Operation
Environment
Building Operation Project Configuration Tool (PCT)
Cause
When the program is first initiated, the values for it is written to the database.
If the “Program executions” Is turned off, the instance values the program had when the backup was taken is not read. Hence the values are set to 0.
On a real AS-P, a Cold start is performed after the restoring of the backup.
When restoring a backup on an AS-P in PCT, one or two cold starts are done, followed by an additional warm start at least for the PCT 2.
Resolution
To get the instance values from the backup when it is restored, the “Program execution”/”Enable program” In PCT should be turned on before the restore is done.
Since a warm start is done for the PCT, the issue regarding Retain level vs. FB Backup property needs to be taken into consideration.