Join our "Ask Me About" community webinar on May 20th at 9 AM CET and 5 PM CET to explore cybersecurity and monitoring for Data Center and edge IT. Learn about market trends, cutting-edge technologies, and best practices from industry experts.
Register and secure your Critical IT infrastructure
APC UPS Data Center & Enterprise Solutions Forum
Schneider, APC support forum to share knowledge about installation and configuration for Data Center and Business Power UPSs, Accessories, Software, Services.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2024-05-16 10:08 AM . Last Modified: 2024-05-16 10:10 AM
Hello
I recently had a problem on a Symmetra UPS. I have the Symmetra UPS and an external battery bank installed. All 13 SYBT5 battery modules have a "Low Capacity" fault. The batteries installed in each module are in good condition.
Please help as to what could be causing all the modules to fail and how to resolve it.
Thank you
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2024-05-17 07:35 AM
I would start with confirming the battery installation date. Next, check what the system indicates is the voltage for each pack.
Than measure the voltage of each pack and compare them to one another. As a interim step eject / remove all extended battery packs.
Reboot the system and confirm the fault goes away. The only fault should be the missing extended battery packs. If so, insert one cartridge and see what the system says.
It’s going to pass or fail one or more cells at some point. Give these first steps a try and report back what you see and observe. 👍
Link copied. Please paste this link to share this article on your social media post.
Create your free account or log in to subscribe to the board - and gain access to more than 10,000+ support articles along with insights from experts and peers.
With achievable small steps, users progress and continually feel satisfaction in task accomplishment.
Usetiful Onboarding Checklist remembers the progress of every user, allowing them to take bite-sized journeys and continue where they left.
of