Help
  • Explore Community
  • Get Started
  • Ask the Community
  • How-To & Best Practices
  • Contact Support
Notifications
Login / Register
Community
Community
Notifications
close
  • Forums
  • Knowledge Center
  • Events & Webinars
  • Ideas
  • Blogs
Help
Help
  • Explore Community
  • Get Started
  • Ask the Community
  • How-To & Best Practices
  • Contact Support
Login / Register
Sustainability
Sustainability

Join our "Ask Me About" community webinar on May 20th at 9 AM CET and 5 PM CET to explore cybersecurity and monitoring for Data Center and edge IT. Learn about market trends, cutting-edge technologies, and best practices from industry experts.
Register and secure your Critical IT infrastructure

SURT Series showing Refused a self-test; UPS is overloaded

APC UPS Data Center & Enterprise Solutions Forum

Schneider, APC support forum to share knowledge about installation and configuration for Data Center and Business Power UPSs, Accessories, Software, Services.

cancel
Turn on suggestions
Auto-suggest helps you quickly narrow down your search results by suggesting possible matches as you type.
Showing results for 
Show  only  | Search instead for 
Did you mean: 
  • Home
  • Schneider Electric Community
  • APC UPS, Critical Power, Cooling and Racks
  • APC UPS Data Center & Enterprise Solutions Forum
  • SURT Series showing Refused a self-test; UPS is overloaded
Options
  • Subscribe to RSS Feed
  • Mark Topic as New
  • Mark Topic as Read
  • Float this Topic for Current User
  • Bookmark
  • Subscribe
  • Mute
  • Printer Friendly Page
Invite a Co-worker
Send a co-worker an invite to the portal.Just enter their email address and we'll connect them to register. After joining, they will belong to the same company.
You have entered an invalid email address. Please re-enter the email address.
This co-worker has already been invited to the Exchange portal. Please invite another co-worker.
Please enter email address
Send Invite Cancel
Invitation Sent
Your invitation was sent.Thanks for sharing Exchange with your co-worker.
Send New Invite Close
Top Experts
User Count
BillP
Administrator BillP Administrator
5060
voidstar_apc
Janeway voidstar_apc
196
Erasmus_apc
Sisko Erasmus_apc
112
Teken
Spock Teken
109
View All

Invite a Colleague

Found this content useful? Share it with a Colleague!

Invite a Colleague Invite
Solved Go to Solution
Back to APC UPS Data Center & Enterprise Solutions Forum
Solved
Anonymous user
Not applicable

Posted: ‎2021-06-28 10:46 PM . Last Modified: ‎2024-03-14 04:01 AM

0 Likes
3
4076
  • Mark as New
  • Bookmark
  • Subscribe
  • Mute
  • Subscribe to RSS Feed
  • Permalink
  • Print
  • Email to a Friend
  • Report Inappropriate Content

Link copied. Please paste this link to share this article on your social media post.

Posted: ‎2021-06-28 10:46 PM . Last Modified: ‎2024-03-14 04:01 AM

SURT Series showing Refused a self-test; UPS is overloaded

I have the ups setup to do a self-test every week. Things were working fine until today. I received the error: Refused a self-test; UPS is overloaded on the web interface. However, I checked the lights on the ups and there are no lights lit indicating a problem. Can anyone help me out as to what I should do?

regards,
zakir

Attachments
Labels
  • Labels:
  • Smart-UPS & Symmetra LX | RM
Reply

Link copied. Please paste this link to share this article on your social media post.

  • All forum topics
  • Previous Topic
  • Next Topic

Accepted Solutions
Techie_apc
Sisko Techie_apc
Sisko

Posted: ‎2021-06-28 10:47 PM . Last Modified: ‎2024-03-14 04:01 AM

0 Likes
0
4075
  • Mark as New
  • Bookmark
  • Subscribe
  • Mute
  • Subscribe to RSS Feed
  • Permalink
  • Print
  • Email to a Friend
  • Report Inappropriate Content

Link copied. Please paste this link to share this article on your social media post.

Posted: ‎2021-06-28 10:47 PM . Last Modified: ‎2024-03-14 04:01 AM

Zakir,

It appears to be an erroneous events from the NMC as the unit passed the manual Self test successfully. However, I request you to reconnect the battery connections firmly in off hours in order to make sure that the batteries are connected properly.

If possible, could you please update the NMC firmware version to the latest version if it has an older firmware version?

Here is the K-base document link which can walk you through the steps to upgrade the NMC firmware.
[http://nam-en.apc.com/cgi-bin/nam_en.cfg/php/enduser/std_adp.php?p_faqid=768]

If this event message persists after upgrading the firmware, then I recommend you to call in the APC Customer Care Center because there might be an issue with the battery charger or the other circuitry.

Have a nice weekend!

See Answer In Context

Reply

Link copied. Please paste this link to share this article on your social media post.

Replies 3
Techie_apc
Sisko Techie_apc
Sisko

Posted: ‎2021-06-28 10:46 PM . Last Modified: ‎2024-03-14 04:01 AM

0 Likes
0
4075
  • Mark as New
  • Bookmark
  • Subscribe
  • Mute
  • Subscribe to RSS Feed
  • Permalink
  • Print
  • Email to a Friend
  • Report Inappropriate Content

Link copied. Please paste this link to share this article on your social media post.

Posted: ‎2021-06-28 10:46 PM . Last Modified: ‎2024-03-14 04:01 AM

Zakir,

Could you please try initiating a manual Self Test through the NMC web interface and check if the unit passes the self test?

Secondly, could you please check the UPS data logs to find out what was the battery capacity and load power consumption when this event log was recorded in the event logs?

Reply

Link copied. Please paste this link to share this article on your social media post.

Anonymous user
Not applicable

Posted: ‎2021-06-28 10:47 PM . Last Modified: ‎2024-03-14 04:01 AM

0 Likes
0
4075
  • Mark as New
  • Bookmark
  • Subscribe
  • Mute
  • Subscribe to RSS Feed
  • Permalink
  • Print
  • Email to a Friend
  • Report Inappropriate Content

Link copied. Please paste this link to share this article on your social media post.

Posted: ‎2021-06-28 10:47 PM . Last Modified: ‎2024-03-14 04:01 AM

Dear Techie
We are initiating a manual Self Test through the NMC and UPS passes the self test. we have made this exercise several time but ups becomes ok at that time and again shows same fault after one or two days if you check the event logs then you will find UPS showing this massages after passing self test 08/08/2009 13:31:33 UPS: The battery is now installed.
08/08/2009 13:31:12 UPS: The battery is not installed properly.
We have attached the snap shorts, event loges and data logs please check them.

Regards,
zakir

Attachments
Reply

Link copied. Please paste this link to share this article on your social media post.

Techie_apc
Sisko Techie_apc
Sisko

Posted: ‎2021-06-28 10:47 PM . Last Modified: ‎2024-03-14 04:01 AM

0 Likes
0
4076
  • Mark as New
  • Bookmark
  • Subscribe
  • Mute
  • Subscribe to RSS Feed
  • Permalink
  • Print
  • Email to a Friend
  • Report Inappropriate Content

Link copied. Please paste this link to share this article on your social media post.

Posted: ‎2021-06-28 10:47 PM . Last Modified: ‎2024-03-14 04:01 AM

Zakir,

It appears to be an erroneous events from the NMC as the unit passed the manual Self test successfully. However, I request you to reconnect the battery connections firmly in off hours in order to make sure that the batteries are connected properly.

If possible, could you please update the NMC firmware version to the latest version if it has an older firmware version?

Here is the K-base document link which can walk you through the steps to upgrade the NMC firmware.
[http://nam-en.apc.com/cgi-bin/nam_en.cfg/php/enduser/std_adp.php?p_faqid=768]

If this event message persists after upgrading the firmware, then I recommend you to call in the APC Customer Care Center because there might be an issue with the battery charger or the other circuitry.

Have a nice weekend!

Reply

Link copied. Please paste this link to share this article on your social media post.

Preview Exit Preview

never-displayed

You must be signed in to add attachments

never-displayed

 
To The Top!

Forums

  • APC UPS Data Center Backup Solutions
  • EcoStruxure IT
  • EcoStruxure Geo SCADA Expert
  • Metering & Power Quality
  • Schneider Electric Wiser

Knowledge Center

Events & webinars

Ideas

Blogs

Get Started

  • Ask the Community
  • Community Guidelines
  • Community User Guide
  • How-To & Best Practice
  • Experts Leaderboard
  • Contact Support
Brand-Logo
Subscribing is a smart move!
You can subscribe to this board after you log in or create your free account.
Forum-Icon

Create your free account or log in to subscribe to the board - and gain access to more than 10,000+ support articles along with insights from experts and peers.

Register today for FREE

Register Now

Already have an account? Login

Terms & Conditions Privacy Notice Change your Cookie Settings © 2025 Schneider Electric

This is a heading

With achievable small steps, users progress and continually feel satisfaction in task accomplishment.

Usetiful Onboarding Checklist remembers the progress of every user, allowing them to take bite-sized journeys and continue where they left.

of