Ask Me About Webinar: Data Center Assets - Modeling, Cooling, and CFD Simulation Join our 30-minute expert session on July 10, 2025 (9:00 AM & 5:00 PM CET), to explore Digital Twins, cooling simulations, and IT infrastructure modeling. Learn how to boost resiliency and plan power capacity effectively.Register now to secure your spot!
SBP16KP with a SURT20KRMXLT
APC UPS Data Center & Enterprise Solutions Forum
Schneider, APC support forum to share knowledge about installation and configuration for Data Center and Business Power UPSs, Accessories, Software, Services.
Send a co-worker an invite to the portal.Just enter their email address and we'll connect them to register. After joining, they will belong to the same company.
You have entered an invalid email address. Please re-enter the email address.
This co-worker has already been invited to the Exchange portal. Please invite another co-worker.
Please enter email address
Send InviteCancel
Invitation Sent
Your invitation was sent.Thanks for sharing Exchange with your co-worker.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2021-06-3001:35 AM. Last Modified: 2024-03-1112:57 AM
SBP16KP with a SURT20KRMXLT
I have a 20 kva SURT20KRMXLT with a SBP16KP Bypass panel running at 208 volts. I want to hardwire feed a distribution breaker panel with 120 volt 15 amps breakers. What is the wiring pattern that you use? ON input and output hardwiring diagram of the ups, the wires are ground , L1, N/L2. What does the slash means? L2 + N ? N only, L2 ONLY?
Link copied. Please paste this link to share this article on your social media post.
Posted: 2021-06-3001:35 AM. Last Modified: 2024-03-1112:57 AM
Your load would be plugged into the SBP16KP(labeled pdu output terminal). Check the link below for details on the wiring. As you can see in the manual, the lines from utility connect directly to the SBP labeled AC Input. The input from the UPS wires to UPS input on the SBP and the output from the UPS wires to UPS output on the SBP. Please reply if you have any questions.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2021-06-3001:35 AM. Last Modified: 2024-03-1112:57 AM
Your load would be plugged into the SBP16KP(labeled pdu output terminal). Check the link below for details on the wiring. As you can see in the manual, the lines from utility connect directly to the SBP labeled AC Input. The input from the UPS wires to UPS input on the SBP and the output from the UPS wires to UPS output on the SBP. Please reply if you have any questions.