Issue
If I have populated a Special Days and Temporary Time Schedule on a point, which schedule will control that point?
Environment
I/NET Time Schedule extension
Cause
There may be an overlap in scheduling that causes a Special day to fall on the same day as a Temporary Time Schedule.
Resolution
In the case of a point having a Special day defined and a Temporary schedule defined, the Temporary Time Schedule will override the Special Days schedule.