Hello,
we have the following setup:
Two server rooms equally equipped. One Smart-UPS SRT 6000 connected with the "hardwired output" to a Service Bypass Panel. The electric load is connected to that SBP.
Part of the load is a vSphere cluster. I have installed the PCNS applicance to shutdown down the environment in a critical situation.
I am confused how to configure the systems. The UPS has 3 outlet groups and a main outlet group. Not a single load is directly connected to the UPS. Can i ignore the settings of the outlet groups as we use the "hardwired output"?
I have attached a screenshot from the PCNS Appliance. Is it correct to attach the ESXi-Hosts to the "unswitched group" because they are connected to the "hardwired output"?
Thanks for your help
Kaspar
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2021-06-28 11:45 AM . Last Modified: 2024-03-15 04:22 AM
Hello Gavan,
thanks for your response 🙂
We are aware that we have to test it but now I am more confident that it will work as planned.
Kind Regards
Kaspar
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2021-06-28 11:45 AM . Last Modified: 2024-03-15 04:22 AM
Looks good to me but I do recommend scheduling a test to ensure it works as it should.
- Gavan
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2021-06-28 11:45 AM . Last Modified: 2024-03-15 04:22 AM
Hello Gavan,
thanks for your response 🙂
We are aware that we have to test it but now I am more confident that it will work as planned.
Kind Regards
Kaspar