Ask our Experts
Didn't find what you are looking for? Ask our experts!
Launch of Consumer/Home Owner registration process! We are pleased to announce the commencement of the Consumer/Home Owner Registration Process on Community. Consumers/Home Owners may now proceed to register by clicking on Login/Register. The process is straightforward and designed to be completed in just a few steps.
Schneider, APC support forum to share knowledge about installation and configuration for Data Center and Business Power UPSs, Accessories, Software, Services.
Search in
Free
EnglishStrengthen your foundational knowledge in Data Centers for free, enroll in this path today and start your learning journey!
Posted: 2021-06-28 06:54 AM . Last Modified: 2024-03-18 01:07 AM
Link copied. Please paste this link to share this article on your social media post.
Posted: 2021-06-28 06:54 AM . Last Modified: 2024-03-18 01:07 AM
Hello,
We use Struxureware DCE to generate a monthly report for our operational compliance team for the energy consumption for the ~40 metered PDUs in our environment, and would like to only have the months energy consumption (kw h) displayed (rather then the kw h consumption since the rail was powered on).
Is there a way to reset the Energy consumption, apart from through the device manager tab in the web browser (as it is not feasible to do this for ~40 PDUs).
Cheers, Matt
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2021-06-28 06:55 AM . Last Modified: 2024-03-18 01:07 AM
There is an OID to do this but unfortunately, it cannot be done as a mass SNMP SET via DCE.
The OIDs for these AP8XXX PDUs are all under .iso.org.dod.internet.private.enterprises.apc.products.hardware.rPDU2 or .1.3.6.1.4.1.318.1.1.26
The OIDs I found for resetting are:
Can you script this to SET each month depending on what value you are resetting?
Link copied. Please paste this link to share this article on your social media post.
Posted: 2021-06-28 06:55 AM . Last Modified: 2024-03-18 01:07 AM
Link copied. Please paste this link to share this article on your social media post.
Posted: 2021-06-28 06:55 AM . Last Modified: 2024-03-18 01:07 AM
Hello,
We use Struxureware DCE to generate a monthly report for our operational compliance team for the energy consumption for the ~40 metered PDUs in our environment, and would like to only have the months energy consumption (kw h) displayed (rather then the kw h consumption since the rail was powered on).
Is there a way to reset the Energy consumption, apart from through the device manager tab in the web browser (as it is not feasible to do this for ~40 PDUs).
Cheers, Matt
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2021-06-28 06:55 AM . Last Modified: 2024-03-18 01:07 AM
There is an OID to do this but unfortunately, it cannot be done as a mass SNMP SET via DCE.
The OIDs for these AP8XXX PDUs are all under .iso.org.dod.internet.private.enterprises.apc.products.hardware.rPDU2 or .1.3.6.1.4.1.318.1.1.26
The OIDs I found for resetting are:
Can you script this to SET each month depending on what value you are resetting?
Link copied. Please paste this link to share this article on your social media post.
Posted: 2021-06-28 06:55 AM . Last Modified: 2024-03-18 01:07 AM
Link copied. Please paste this link to share this article on your social media post.
Posted: 2021-06-28 06:55 AM . Last Modified: 2024-03-18 01:07 AM
Angela, you are a rockstar!
I didn't even think about using SNMP to set values. Thanks!
Link copied. Please paste this link to share this article on your social media post.
You’ve reached the end of your document
Create your free account or log in to subscribe to the board - and gain access to more than 10,000+ support articles along with insights from experts and peers.