Greetings,
I have been assigned a task for power outage after action plan and I was wonder if anyone have a check list template or action plan that would like to share. We have small shops without generators throughout our network, I am looking for a simple template to fill with steps to check during and after the power outage?
Thanks in advance
Link copied. Please paste this link to share this article on your social media post.
Link copied. Please paste this link to share this article on your social media post.
Posted: 2021-11-06 07:32 PM
Not quite into the realm of DCE but let me share some ideas that may help you get started.
1. Keep an eye of the output load before and after the power outage
2. Is common to have air conditioner unit directly into the unprotected power so you need to look for temp readings
3. Temp not only hurts the it/comm load but also the UPS.
Hope this helps.
Link copied. Please paste this link to share this article on your social media post.
You’ve reached the end of your document
Create your free account or log in to subscribe to the board - and gain access to more than 10,000+ support articles along with insights from experts and peers.