APC UPS Data Center & Enterprise Solutions Forum
Schneider Electric support forum for our Data Center and Business Power UPS, UPS Accessories, Software, Services, and associated commercial products designed to share knowledge, installation, and configuration.
Posted: 2021-07-08 01:47 AM
This was originally posted on APC forums on 10/6/2015
I've found the following topic about upgrading the vmware tools
would there be any issues doing this in a live production environment ?
Posted: 2021-07-08 01:47 AM
This reply was originally posted by Bill on APC forums on 10/6/2015
Ben,
No. The Upgrade is quick however I would not do the upgrade when there was a potential of a power outage i.e. storm.
Posted: 2021-07-08 01:47 AM
This reply was originally posted by Bill on APC forums on 10/6/2015
Ben,
No. The Upgrade is quick however I would not do the upgrade when there was a potential of a power outage i.e. storm.
Create your free account or log in to subscribe to the forum - and gain access to more than 10,000+ support articles along with insights from experts and peers.